Guide to Planning Bridge Power Systems for Data Centers

As grid interconnection delays stretch into years, bridge power lets data center owners begin operations and generate revenue sooner.

Article Updated on: October 16, 2026

Global demand for data centers has surged, yet the power grid's capacity and its ability to interconnect new loads have not kept pace. After data center construction is complete, owners typically wait several years for full grid interconnection. As more data centers are built, and on expedited timelines, delays will only increase. Bridge power systems are becoming crucial investments that allow data center owners to power the facility during commissioning and begin operations sooner, reducing time-to-revenue.

 

What is bridge power?

Bridge power is temporary power generation that lets data center owners begin operations before permanent utility interconnection is complete. Because full grid interconnection can take several years after construction finishes, bridge power systems, including generators, battery energy storage systems (BESS) or hybrid microgrids, let operators begin commissioning sooner. This reduces time-to-revenue and gives owners flexibility in site selection while they wait on the grid.

 

What are the benefits of bridge power systems?

In addition to bridging the gap between construction and utility power, bridge power solutions offer other advantages, including:

  • Flexible site selection: Data center developers gain the freedom to build in optimal locations rather than being tied to locations with available grid capacity.
  • Increased sustainability: Hybrid solutions and microgrids that incorporate batteries and solar panels or alternatively fueled generators reduce carbon emissions, helping data center operators meet sustainability targets.
  • Long-term backup power: Bridge power solutions such as microgrids can be repurposed as backup power once the facility is fully connected to the grid, adding capacity and resilience.

How do you design an effective bridge power system?

Designing a temporary data center power solution is a complex undertaking. Below is a quick look at some of the key steps involved.

1. Identify the permits required

Work with relevant authorities to understand applicable federal, state, and local regulations and seek the required permits. United Rentals can help customers navigate the permitting process.

2. Assess the power requirements

Perform a detailed load analysis for IT equipment, cooling systems, lighting, mechanical systems and all other power loads. Factor in future growth projections. A bridge power solution should be modular and scalable to meet evolving power needs. Add a safety margin on top to ensure sufficient, uninterrupted power.

3. Plan for redundancy and reliability

Redundancy requires careful planning. Work with a knowledgeable bridge power partner to identify optimal redundancy strategies such as N-1, N+1 and 2N.

Pay special attention to ramp loads and power profiles to maximize efficiencies and minimize fuel costs. Adherence to transients, capacitive and other power profile features is the key to reliability and continuous output.

4. Look to diesel generators and cleaner power options

Tier 4 Final diesel generators are the traditional go-to solutions for bridge power. United Rentals offers towable generators ranging from 13 kW to 2,000 kW and the ability to parallel generators as loads grow or complexity increases.

Hybrid generators and propane generators are more sustainable alternatives with lower service costs. Unlike diesel generators, they aren’t susceptible to wet stacking.

In areas where hydrogen fuel is readily available, hydrogen-powered fuel cells are another option to consider for clean, reliable primary or backup power. Though hydrogen is expensive, hydrogen-powered fuel cells are more efficient than fossil fuel generators. That’s because hydrogen creates more energy per pound of fuel than gas or diesel. Like diesel generators, these modular units can be linked together to meet large power demands.

5. Integrate battery energy storage systems (BESS)

Battery energy storage systems (BESS) improve the resilience of power generation systems, reduce fuel costs and increase sustainability.

When paired with a generator, a BESS optimizes generator runtime, dramatically reducing fuel consumption and carbon emissions. An automated load management system turns the generator on and off as needed and powers the load with the battery whenever possible.

6. Plan for efficient power distribution

Safe, effective power distribution is key to ensuring reliable and flexible delivery of temporary power across all areas of the data center. United Rentals offers a full inventory of power distribution equipment and can help customers tailor a distribution system that integrates seamlessly with generators and BESS and supports cost savings and sustainability.

Careful planning of distribution infrastructure also sets the foundation for a smooth transition to permanent utility power, avoiding costly downtime or rework.

Designing an optimal power distribution system entails:

  • Sizing power distribution panels for the projected load, factoring in future load increases
  • Using step-up or step-down transformers to match voltage requirements between generators, batteries and electrical infrastructure to optimize efficiency and protect sensitive equipment
  • Arranging flexible cabling, transfer switches and power boxes to allow easy rerouting and safe connections throughout the site

7. Implement remote monitoring

Remotely monitoring generators helps maintain power system reliability and reduce equipment-related downtime. It’s essential when powering mission-critical loads.

Telematics-equipped generators and Total Control®, United Rentals’ cloud-based worksite management platform, enable remote monitoring of engine performance and low-fuel alerts.

Which bridge power system is right for your data center?

Choosing the right bridge power source for your data center project depends on your project’s budget, fuel availability and sustainability goals.

Power Source

Sustainability

Cost

Reliability

Best Used For

Diesel generators

Lower (Traditional fossil fuel)

Lower upfront cost

High (Proven and widely available)

Primary bridge power for large, immediate loads

Natural gas / propane generators

Moderate (Cleaner than diesel)

Lower service costs

High (Not susceptible to wet stacking)

Sites with reliable gas or propane access seeking lower service costs

Hydrogen-powered fuel cells

High (Clean and efficient energy per pound of fuel)

Higher (Hydrogen fuel is expensive)

High (Modular units link together for large demands)

Areas with available hydrogen fuel seeking clean primary or backup power

Battery energy storage systems (BESS)

High (Reduces fuel consumption and emissions)

Lower long-term fuel costs

High (Optimizes generator runtime and adds resilience)

Pairing with generators to cut fuel use and improve sustainability

Partner with United Rentals for bridge power planning

In today’s fast-paced, hypercompetitive data center environment, reliable, scalable bridge power systems are vital strategic assets that help data center owners mitigate utility interconnection delays and begin serving customers, and generating revenue, sooner.

Partnering with a temporary power solutions provider that brings deep knowledge and years of experience in the data center industry helps ensure a successful outcome. United Rentals can engineer, install and service a custom bridge power system or guide customers to the optimal equipment for their bridge power needs.

Turn to United Rentals as a trusted partner for rapidly deployable off-grid power solutions tailored to the application and budget, complete with end-to-end support.

 

Frequently asked questions

What is bridge power used for in data centers?

Bridge power supplies temporary electricity to data centers during construction and commissioning, before permanent utility interconnection is complete. This lets operators begin serving customers and generating revenue sooner rather than waiting years for full grid access.

How long can a bridge power system operate before grid interconnection?

Bridge power systems are built to run for several years to outlast interconnection delays. Modular equipment, such as towable generators and battery energy storage systems (BESS), allows the system to scale alongside the facility's power demands.

Can bridge power systems be reused after grid connection?

Yes, bridge power solutions such as microgrids can be repurposed as long-term backup power once the facility is fully connected to the utility grid.

Is bridge power more sustainable than traditional backup power?

Yes, bridge power can be more sustainable than traditional backup power. Hybrid generators, propane generators, hydrogen fuel cells and battery energy storage systems (BESS) reduce fuel consumption and carbon emissions compared with diesel-only setups. This helps data center operators meet their company's sustainability initiatives.